| |
Change Orders in Arizona Construction
John R.
Hoopes
However complete your contract documents are believed
to be, changes frequently occur. When the contractor claims that a change has
occurred, the owner's concern is to be sure there really is a change and that
the contractor is not trying to get paid for work that is in fact part of the
original scope of work. For the contractor's part, he wants to make sure that he
is paid fairly for extra work performed.
Under certain circumstances, the owner or the owner's representative may
unilaterally direct the contractor to perform extra work. For example, certain
American Institute of Architects (AIA) forms — e.g., § 7.3.1, AIA Document 201 —
provide for a "construction change directive," which obligates the contractor to
perform additional work with the appropriate adjustment of the contract
price/time to be determined later by procedures detailed in the contract
documents. This right is not, of course, unlimited, and if the change is
sufficiently significant in scope, it may constitute what is called a "cardinal
change" that justifies termination of the contract.
More typically, changes are negotiated and stated in written change orders.
Although the urgencies of a project do not often permit it, whenever possible a
written change order should be prepared and signed before the extra work is
performed. And while the AIA forms include a suggested change order, no
particular form is required for a change order to be enforceable as long as it
satisfies the basic requirements of a contract.
At a minimum, the written change order should:
-
specify in as much detail as possible the change in the work;
-
state the resulting change in the contract price; and
-
if applicable, note the resulting change in the contract time.
One of the most frequent misconceptions about change orders is the belief that
the owner may rely on contract provisions stating that only written change
orders may be enforced.
In the case of Sitkin v. Smith (35 Ariz. 236, 276 P. 521 [1929]), the Arizona
Supreme Court considered a contract that purported to bar oral modification. The
court held that such a bar "does not prevent the parties from subsequently
making another and different agreement, or from orally altering, changing or
modifying the written contract when they mutually agree thereon." (35 Ariz. at
230).
An owner's conduct may constitute a waiver of a contract's prohibition against
oral change orders. In Pioneer Roofing Co. v. Mardian Construction Co., 152
Ariz. 455, 733 P.2d 652 [App. 1986]), the court ruled that the owner's "'go
ahead actions' ... constituted a waiver of the provision of the supplementary
conditions to the general contract documents that provided: 'Claims for
additional compensation, account of extra work done, will not be recognized
unless such actual work has been authorized in advance and in writing by the
architect'".
These types of change orders are sometimes called "constructive change orders."
While possible, claims based on unwritten change orders can be difficult to
prove. The contractor's prosecution of such claims is helped to the extent that
job logs and correspondence confirm communications with the owner regarding the
additional work. Likewise, the owner can reduce the risk of change orders if he
confirms in writing his advice to the contractor that a change order request has
been denied, the proposed work is within the scope of the original contract, and
the contractor will not receive additional compensation for that work.
The amount of recovery in the case of an oral or constructive change order will
usually be governed by principles of what the law calls quantum meruit, or
"unjust enrichment." According to this rule of law, where in the circumstances
one may not rely upon a contract to define the compensation to be paid, one may
recover the reasonable value of the work or materials provided. Reasonable value
is typically not determined by the cost to the contractor/supplier, but instead
by reference to the value realized by the owner. Hoopes,
Adams & Alexander, PLC, is a Chandler, Arizona, law firm offering services to
Phoenix-area clients in the areas of estate planning, entity formation,
commercial and real estate transactions, and civil litigation. |
|